No. 1 Road Rehabilitation

Share No. 1 Road Rehabilitation on Facebook Share No. 1 Road Rehabilitation on Twitter Share No. 1 Road Rehabilitation on Linkedin Email No. 1 Road Rehabilitation link

Kia ora, welcome to the No.1 Road rehabilitation project page. Here, you’ll find everything you need to know about the project, including latest updates, and a timeline of upcoming steps. Check out the information on the right-hand side of this page for all this and more.


About the project

No.1 Road is getting a partial reconstruction to improve safety and make it more user friendly. The $3.2 million project will be completed over two years and will include widening two of the middle sections of the road. The road will also be lowered at the intersection with Cannell Farm Drive, in preparation for future extension works to join the two roads. The first section of works, spanning property numbers 58 to 195, started on 1 October 2024, and is expected to be completed by late August 2025.

What’s happening now?

19 June 2025

Relocation of the Chorus cables continues. The works have been delayed by the heavy rainstorms over the past couple of weeks.

Our main contactor is making good progress with the stormwater discharge at No. 73.

The weather caused some minor damage that will be repaired by the contractor.


29 May 2025

We've finished relocating the watermain under the widened road surface, and new ducts are in place for the Chorus telecommunication cables, which we expect to be installed next week.

Our contractor is busy building a new stormwater discharge facility at the downhill end of the road (at no.73). This work includes the development of new wetland areas and plantings to improve water quality, support wildlife and reduce flooding.

Access track and new stormwater pipes.

Development of new wetland.


Kia ora, welcome to the No.1 Road rehabilitation project page. Here, you’ll find everything you need to know about the project, including latest updates, and a timeline of upcoming steps. Check out the information on the right-hand side of this page for all this and more.


About the project

No.1 Road is getting a partial reconstruction to improve safety and make it more user friendly. The $3.2 million project will be completed over two years and will include widening two of the middle sections of the road. The road will also be lowered at the intersection with Cannell Farm Drive, in preparation for future extension works to join the two roads. The first section of works, spanning property numbers 58 to 195, started on 1 October 2024, and is expected to be completed by late August 2025.

What’s happening now?

19 June 2025

Relocation of the Chorus cables continues. The works have been delayed by the heavy rainstorms over the past couple of weeks.

Our main contactor is making good progress with the stormwater discharge at No. 73.

The weather caused some minor damage that will be repaired by the contractor.


29 May 2025

We've finished relocating the watermain under the widened road surface, and new ducts are in place for the Chorus telecommunication cables, which we expect to be installed next week.

Our contractor is busy building a new stormwater discharge facility at the downhill end of the road (at no.73). This work includes the development of new wetland areas and plantings to improve water quality, support wildlife and reduce flooding.

Access track and new stormwater pipes.

Development of new wetland.