No. 1 Road Rehabilitation

Share No. 1 Road Rehabilitation on Facebook Share No. 1 Road Rehabilitation on Twitter Share No. 1 Road Rehabilitation on Linkedin Email No. 1 Road Rehabilitation link

Kia ora, welcome to the No.1 Road rehabilitation project page. Here, you’ll find everything you need to know about the project, including latest updates, and a timeline of upcoming steps. Check out the information on the right-hand side of this page for all this and more.


About the project

No.1 Road is getting a partial reconstruction to improve safety and make it more user friendly. The $3.2 million project will be completed over two years and will include widening two of the middle sections of the road. The road will also be lowered at the intersection with Cannell Farm Drive, in preparation for future extension works to join the two roads. The first section of works, spanning property numbers 58 to 195, started on 1 October 2024, and is expected to be completed by late February 2025.

What’s happening now?

27 February 2025

Relocation of the existing water main is underway, and we've finished new stormwater drainage at number 186. Construction of stormwater discharge at number 142 is ongoing. And we've also started minor earthworks and road surfacing work between numbers 80 and 98.



13 February 2025

Over the past week we've installed stormwater pipes and manholes at numbers 142 and 186.

We've also relocated the existing fibre optic cable draw-pit. This is a chamber used for removing damaged cables and pulling through new cables.


Kia ora, welcome to the No.1 Road rehabilitation project page. Here, you’ll find everything you need to know about the project, including latest updates, and a timeline of upcoming steps. Check out the information on the right-hand side of this page for all this and more.


About the project

No.1 Road is getting a partial reconstruction to improve safety and make it more user friendly. The $3.2 million project will be completed over two years and will include widening two of the middle sections of the road. The road will also be lowered at the intersection with Cannell Farm Drive, in preparation for future extension works to join the two roads. The first section of works, spanning property numbers 58 to 195, started on 1 October 2024, and is expected to be completed by late February 2025.

What’s happening now?

27 February 2025

Relocation of the existing water main is underway, and we've finished new stormwater drainage at number 186. Construction of stormwater discharge at number 142 is ongoing. And we've also started minor earthworks and road surfacing work between numbers 80 and 98.



13 February 2025

Over the past week we've installed stormwater pipes and manholes at numbers 142 and 186.

We've also relocated the existing fibre optic cable draw-pit. This is a chamber used for removing damaged cables and pulling through new cables.