October 2024

Works begin

In the first few weeks, crews focused on setting up the sitelocating underground utilities, and working on stormwater drainage upgrades, which are needed due to the road being widened.

01 November 2024

Widening the road

Now that we've completed the behind-the-scenes work, there is more to see, with diggers shifting dirt around as we prepare to widen the road. We've been busy:

  • Digging out the grass berms - this week we completed the stretch of road between numbers 114 and 168.
  • Marking out where services like power and fibre will go, and any areas where existing services might be affected by the works.
  • Creating a temporary road to bring drainage materials on site.
21 November 2024

Construction of new stormwater drainage

21 November 2024

Construction of the new stormwater drainage system is underway. To safeguard existing power and broadband services, our contractor is working closely with Powerco, Chorus and Tuatahi First Fibre to make sure cables are protected and/or relocated so they aren't damaged by the work.

For heavy machinery enthusiasts, here's the line-up of equipment currently on site:

  • 50T excavator
  • 20T long reach excavator
  • Two 14T excavators
  • 16T excavator
  • D3 bulldozer
  • Six-wheeler
  • Two 4-wheelers
  • Watercart
  • Tractor broom
  • 120 grader
  • Cat roller
  • 4T roller
21 November 2024

Stormwater works continue

We're continuing with the stormwater drainage upgrades this week, with an archaeologist on hand to monitor the ground for any pre-European material.

02 December 2024

1200 diameter main installed

Construction of drainage upgrades continues with installation of the 1200 diameter stormwater main, manholes and driveway culverts. Buried utility services are impeding progress in some locations.

15 January 2025

Pavement widening work starts

We're continuing with earthworks and stormwater drainage construction, and we've also started pavement widening work. Check out the latest pics below:


20 January 2025

Earthworks completed between numbers 107-133

Earthworks have been completed between house numbers 107 and 133. We've also installed multiple culverts and replaced water services where they were found to be laid too shallow.

Pavement works are ongoing, between numbers 107 and 114.