Cookies help us to understand how you use our website so that we can provide you with the best experience when you are on our site. To find out more, read our privacy policy and cookie policy.
Manage Cookies
A cookie is information stored on your computer by a website you visit. Cookies often store your settings for a website, such as your preferred language or location. This allows the site to present you with information customized to fit your needs. As per the GDPR law, companies need to get your explicit approval to collect your data. Some of these cookies are ‘strictly necessary’ to provide the basic functions of the website and can not be turned off, while others if present, have the option of being turned off. Learn more about our Privacy and Cookie policies. These can be managed also from our cookie policy page.
Strictly necessary cookies(always on):
Necessary for enabling core functionality. The website cannot function properly without these cookies. This cannot be turned off. e.g. Sign in, Language
Analytics cookies:
Analytical cookies help us to analyse user behaviour, mainly to see if the users are able to find and act on things that they are looking for. They allow us to recognise and count the number of visitors and to see how visitors move around our website when they are using it. Tools used: Google Analytics
Social media cookies:
We use social media cookies from Facebook, Twitter and Google to run Widgets, Embed Videos, Posts, Comments and to fetch profile information.
As part of our Long Term Plan 2024 - 2034, we need to change the timing of some projects to reduce the impact on rates – What do you think?
Share As part of our Long Term Plan 2024 - 2034, we need to change the timing of some projects to reduce the impact on rates – What do you think? on FacebookShare As part of our Long Term Plan 2024 - 2034, we need to change the timing of some projects to reduce the impact on rates – What do you think? on TwitterShare As part of our Long Term Plan 2024 - 2034, we need to change the timing of some projects to reduce the impact on rates – What do you think? on LinkedinEmail As part of our Long Term Plan 2024 - 2034, we need to change the timing of some projects to reduce the impact on rates – What do you think? link
Consultation has concluded
CLOSED: Consultation has concluded. Please see key dates within the timeline for next steps.
The current picture
Nobody likes hearing about rates going up. Especially on top of all the other rising household costs. We hear you. Council has its own budget to balance, and we are facing increased costs too. Roads and water supply are 27% more expensive to build, and sewerage systems 30% more expensive than they were three years ago when we put together our last Long Term Plan – according to Local Government New Zealand.
CLOSED: Consultation has concluded. Please see key dates within the timeline for next steps.
The current picture
Nobody likes hearing about rates going up. Especially on top of all the other rising household costs. We hear you. Council has its own budget to balance, and we are facing increased costs too. Roads and water supply are 27% more expensive to build, and sewerage systems 30% more expensive than they were three years ago when we put together our last Long Term Plan – according to Local Government New Zealand.
The changing landscape
We're doing our best to keep costs down for you, but to achieve this we’ve had to make some tough choices. To strike a balance between affordability and ensuring our District keeps moving forward, we’re asking you to join us in considering the options.
Framing the future
We are looking at changing the timing of some projects so we can spread out some of the costs over future years and reduce the immediate impact on you. Most importantly, we want to ensure that you're getting the best value for your money while still receiving the services you rely on every day. The projects in the table on the next page are ones we think are important to the community and deliver services the community have told us you want, so should be delivered, however they are not pressing, and the timing has been considered. Our debt profile increases up to $427m in 2030 and average rates increases of 13.6% in year one (2024/25), 10.4% in year two (2025/26) and 8.4% in years 3-10 (2027-34).
There are two options:
1. Our preferred option - Change the timing of some projects to reduce the immediate impact on rates (2024/25) and then spread out some of the costs in future years - 13.6% rate increase in Year One (2024/25).
Impact on rates: 13.6% rate increase in 2024/25 (Year One). This will move out rate increases to later years.
Impact on debt over 10 years: This will reduce debt in the short term, but will increase overall debt across the ten years, due cost inflation.
Impact on levels of service: Despite changes in project schedules, efforts are made to sustain the existing levels of service. However, due to these project timing adjustments, the delivery on some agreed increases in levels of service are delayed compared to previous plans.
2. Stick to the original timing of some projects - resulting in a 24.4% rate increase in Year One (2024/25).
Impact on rates: 24.4% rate increase in 2024/25 (Year One).
Impact on debt: This will increase debt in the short term, but will reduce overall debt across the ten years, due avoiding cost inflation.
Impact on levels of service: No impact on levels of service.
What are the projects we're talking about?
Katikati-Waihī Beach
Project Description
Prior Plan Timing
Original Cost
Rephased Timing
Rephased Cost
Moore Park Toilets – upgrade of existing facilities
2024
$63,101
2027
$276,750
New Northern Harbour Boat Ramp
2024
$4.93m
Outside of the 10-year plan
Kaimai
Project Description
Prior Plan Timing
Original Cost
Rephased Timing
Rephased Cost
Ōmokoroa Ferry Infrastructure – to enable a commuter ferry service from Ōmokoroa to Tauranga
2028
$3m
2030
$3.60m
New Ōmokoroa Library and Service Centre
Not in prior plan
-
2033
$754,200*
Maketu-Te Puke
Project Description
Prior Plan Timing
Original Cost
Rephased Timing
Rephased Cost
Te Puke Swimming Pool – new indoor facility to replace the existing pool
2025
$15.69m
2028
$17.33m
Paengaroa Sports Field - upgrade
2027
$320,915
2030
$341,208
New Maketu Community Hub
Not in prior plan
-
2029
$3.55m
Arawa Road Reserve Development
Not in prior plan
-
2028
$62,205
Pongakawa Heritage House Car Park Development
Not in prior plan
-
2028
$138,130
Sub-regional
Project Description
Prior Plan Timing
Original Cost
Rephased Timing
Rephased Cost
TECT Park Adventure Playground
2025
$1.95m
2029
$2.25m
TECT Park Te Matai Sealed Driver Training Area
2025
$411,200
2027
$455,198
Council Contribution to Sub-Regional Coastal Park
2027
$514,000
2029
$593,156
*This number reflects costs in years 2033-34 of this plan and does not consider future costs outside of the 10 years.
As part of our Long Term Plan 2024 - 2034, we need to change the timing of some projects to reduce the impact on rates – What do you think? is currently at this stage
This consultation is open for contributions.
Consultation closes - 17 June
this is an upcoming stage for As part of our Long Term Plan 2024 - 2034, we need to change the timing of some projects to reduce the impact on rates – What do you think?
Under review - June/July
this is an upcoming stage for As part of our Long Term Plan 2024 - 2034, we need to change the timing of some projects to reduce the impact on rates – What do you think?
Contributions to this consultation are closed for evaluation and review.
Council deliberations - August
this is an upcoming stage for As part of our Long Term Plan 2024 - 2034, we need to change the timing of some projects to reduce the impact on rates – What do you think?
Council will review all feedback submitted.
Long Term Plan 2024-2034 adopted - September 2024
this is an upcoming stage for As part of our Long Term Plan 2024 - 2034, we need to change the timing of some projects to reduce the impact on rates – What do you think?