As part of our Long Term Plan 2024 - 2034, we need to change the timing of some projects to reduce the impact on rates – What do you think?

Share As part of our Long Term Plan 2024 - 2034, we need to change the timing of some projects to reduce the impact on rates – What do you think? on Facebook Share As part of our Long Term Plan 2024 - 2034, we need to change the timing of some projects to reduce the impact on rates – What do you think? on Twitter Share As part of our Long Term Plan 2024 - 2034, we need to change the timing of some projects to reduce the impact on rates – What do you think? on Linkedin Email As part of our Long Term Plan 2024 - 2034, we need to change the timing of some projects to reduce the impact on rates – What do you think? link

Consultation has concluded

CLOSED: Consultation has concluded. Please see key dates within the timeline for next steps.

The current picture 

Nobody likes hearing about rates going up. Especially on top of all the other rising household costs. We hear you. Council has its own budget to balance, and we are facing increased costs too. Roads and water supply are 27% more expensive to build, and sewerage systems 30% more expensive than they were three years ago when we put together our last Long Term Plan – according to Local Government New Zealand.

The changing landscape 

We're doing our best to keep costs

CLOSED: Consultation has concluded. Please see key dates within the timeline for next steps.

The current picture 

Nobody likes hearing about rates going up. Especially on top of all the other rising household costs. We hear you. Council has its own budget to balance, and we are facing increased costs too. Roads and water supply are 27% more expensive to build, and sewerage systems 30% more expensive than they were three years ago when we put together our last Long Term Plan – according to Local Government New Zealand.

The changing landscape 

We're doing our best to keep costs down for you, but to achieve this we’ve had to make some tough choices. To strike a balance between affordability and ensuring our District keeps moving forward, we’re asking you to join us in considering the options.

Framing the future 

We are looking at changing the timing of some projects so we can spread out some of the costs over future years and reduce the immediate impact on you. Most importantly, we want to ensure that you're getting the best value for your money while still receiving the services you rely on every day. The projects in the table on the next page are ones we think are important to the community and deliver services the community have told us you want, so should be delivered, however they are not pressing, and the timing has been considered. Our debt profile increases up to $427m in 2030 and average rates increases of 13.6% in year one (2024/25), 10.4% in year two (2025/26) and 8.4% in years 3-10 (2027-34).

There are two options:

1. Our preferred option - Change the timing of some projects to reduce the immediate impact on rates (2024/25) and then spread out some of the costs in future years - 13.6% rate increase in Year One (2024/25).

  • Impact on rates: 13.6% rate increase in 2024/25 (Year One). This will move out rate increases to later years.
  • Impact on debt over 10 years: This will reduce debt in the short term, but will increase overall debt across the ten years, due cost inflation.
  • Impact on levels of service: Despite changes in project schedules, efforts are made to sustain the existing levels of service. However, due to these project timing adjustments, the delivery on some agreed increases in levels of service are delayed compared to previous plans.

2. Stick to the original timing of some projects - resulting in a 24.4% rate increase in Year One (2024/25).

  • Impact on rates: 24.4% rate increase in 2024/25 (Year One). 
  • Impact on debt: This will increase debt in the short term, but will reduce overall debt across the ten years, due avoiding cost inflation.
  • Impact on levels of service: No impact on levels of service.

What are the projects we're talking about?

Katikati-Waihī Beach 

Project DescriptionPrior Plan TimingOriginal CostRephased TimingRephased Cost
Moore Park Toilets – upgrade of existing facilities
2024
$63,101
2027
$276,750
New Northern Harbour Boat Ramp
2024

$4.93m
Outside of the 10-year plan


 Kaimai

Project Description
Prior Plan Timing
Original Cost
Rephased Timing
Rephased Cost
Ōmokoroa Ferry Infrastructure – to enable a commuter ferry service from Ōmokoroa to Tauranga
2028
$3m
2030
$3.60m
New Ōmokoroa Library and Service Centre
Not in prior plan
-2033
$754,200*


Maketu-Te Puke

Project DescriptionPrior Plan TimingOriginal CostRephased TimingRephased Cost
Te Puke Swimming Pool – new indoor facility to replace the existing pool
2025$15.69m
2028$17.33m
Paengaroa Sports Field - upgrade
2027$320,915
2030$341,208
New Maketu Community Hub
Not in prior plan -2029$3.55m
Arawa Road Reserve Development
Not in prior plan -2028$62,205
Pongakawa Heritage House Car Park Development
Not in prior plan -2028$138,130


Sub-regional

Project Description
Prior Plan Timing
Original Cost
Rephased Timing
Rephased Cost
TECT Park Adventure Playground
2025$1.95m
2029
$2.25m
TECT Park Te Matai Sealed Driver Training Area
2025$411,200
2027
$455,198
Council Contribution to Sub-Regional Coastal Park
2027$514,000
2029
$593,156


*This number reflects costs in years 2033-34 of this plan and does not consider future costs outside of the 10 years.