Maketū Road culvert upgrade
Kia ora, welcome to the Maketū Road culvert upgrade project page. Here, you’ll find everything you need to know about the project, including latest updates, and a timeline of upcoming steps.
Project update - 20 November
Maketū Road night works - temporary road closures
From Sunday night, Maketū Road will be closed at the Spencer Avenue intersection for three consecutive nights while we excavate the culvert pipe.
A full road closure will give machinery and workers more room to operate safely, allowing the work to be completed faster and potentially shortening the overall project by a week or two.
Maketū Road will be closed on either side of the Spencer Avenue intersection at the following times:
• Sunday 22 November, 8pm – 4am
• Monday 23 November, 8pm – 4am
• Tuesday 24 November, 8pm – 4am
Guided access will be available for residents living in the immediate area.
Detours
Temporary traffic management and signs will be in place, with detours shown on the map below:

From the eastern side of the closure (red line):
- Via Wilson Road, State Highway 2, Te Puke Highway (Pacific Coast Highway), and Maketū Road (red line).
From the western side of the closure:
- Via Maketu Road, Kaituna Road, Te Tumu Road, Te Puke Highway (Pacific Coast Highway), State Highway 2 and Wilson Road and Maketū Road (blue line).
- Alternatively, use the shorter route shown by the orange-blue lines
We appreciate that night works may cause some temporary noise disruption from machinery and lighting. Every effort will be made to minimise these impacts and complete the work as quickly and safely as possible.
Thank you for your understanding. Getting the work done in a shorter timeframe means normal traffic movements can resume sooner, reducing the overall disruption to the community.

Project Update - 11 November
We’ve appointed Joubert Pilat Limited (JPL) to carry out the culvert upgrade works, and they’re getting ready to start work on Monday 16 November, subject to the weather and necessary regulatory approvals.
Some of the materials have already arrived on site, including one of the new culvert headwalls pictured below.
These are 'split' headwalls, which means they come in one piece and are cut so they can be positioned to fit around the two culvert pipes, with the middle section concreted to complete the headwall.
Traffic management will vary as work progresses, with temporary traffic lights likely to be used for much of the project. Short road closures may also be needed for some activities, but these will be notified in advance.

About the project

We are upgrading the culvert under Maketū Road, at the Ōtumakoro Stream crossing, to help improve waterflow and reduce flooding during heavy rain.
The existing culvert, near Spencer Avenue West, has long been identified as a constriction point in the stormwater network, limiting how much water can pass through during significant rainfall events.
The upgrade is expected to reduce water levels upstream during storm events, decrease the frequency of flooding affecting nearby properties, and reduce how often the road closes due to overtopping at Maketū Road.
🛠️ The $550,000 project will see a second culvert installed and the existing culvert extended.
🚶 A new 2.5 metre shared pathway will also be built to improve safety for people walking and cycling through the area.
🗓️ The work is scheduled to start in early November and be completed by the end of January 2027.
🚦 Maketū Road will remain open during most of the work, but will be reduced to one lane, with temporary traffic lights in place. Short duration road closures may be required at times, but we will give you advance notice when these are coming up.
🐟 The work is being done over the summer, when water levels are lower, and to avoid the fish spawning season. Acquatic life has also been considered in the design. Raised ridges inside the culverts will create pockets of calmer water where fish can rest on their journey upstream, while fish-friendly floodgate valves will help them move through the stream.
⛏️ Archaeological monitoring will be undertaken during construction, with tangata whenua kept informed and involved throughout the project.
We know summer is a busy time in Maketū and there will be some inconvenience, but it’s the best time to do the work safely, while minimising impacts on the stream, fish and other wildlife.
We appreciate your patience while we carry out this important upgrade, which will help reduce flooding and improve the resilience of the area’s stormwater network.