Maketū Road culvert upgrade

Share Maketū Road culvert upgrade on Facebook Share Maketū Road culvert upgrade on X (formerly Twitter) Share Maketū Road culvert upgrade on Linkedin Email Maketū Road culvert upgrade link

Kia ora, welcome to the Maketū Road culvert upgrade project page. Here, you’ll find everything you need to know about the project, including latest updates, and a timeline of upcoming steps.

Project update - 20 November

Maketū Road night works - temporary road closures

From Sunday night, Maketū Road will be closed at the Spencer Avenue intersection for three consecutive nights while we excavate the culvert pipe.

A full road closure will give machinery and workers more room to operate safely, allowing the work to be completed faster and potentially shortening the overall project by a week or two.

Maketū Road will be closed on either side of the Spencer Avenue intersection at the following times:

• Sunday 22 November, 8pm – 4am

• Monday 23 November, 8pm – 4am

• Tuesday 24 November, 8pm – 4am

Guided access will be available for residents living in the immediate area.


Detours

Temporary traffic management and signs will be in place, with detours shown on the map below:

From the eastern side of the closure (red line):

  • Via Wilson Road, State Highway 2, Te Puke Highway (Pacific Coast Highway), and Maketū Road (red line).

From the western side of the closure:

  • Via Maketu Road, Kaituna Road, Te Tumu Road, Te Puke Highway (Pacific Coast Highway), State Highway 2 and Wilson Road and Maketū Road (blue line).
  • Alternatively, use the shorter route shown by the orange-blue lines

We appreciate that night works may cause some temporary noise disruption from machinery and lighting. Every effort will be made to minimise these impacts and complete the work as quickly and safely as possible.

Thank you for your understanding. Getting the work done in a shorter timeframe means normal traffic movements can resume sooner, reducing the overall disruption to the community.


Project Update - 11 November

We’ve appointed Joubert Pilat Limited (JPL) to carry out the culvert upgrade works, and they’re getting ready to start work on Monday 16 November, subject to the weather and necessary regulatory approvals.

Some of the materials have already arrived on site, including one of the new culvert headwalls pictured below.

These are 'split' headwalls, which means they come in one piece and are cut so they can be positioned to fit around the two culvert pipes, with the middle section concreted to complete the headwall.

Traffic management will vary as work progresses, with temporary traffic lights likely to be used for much of the project. Short road closures may also be needed for some activities, but these will be notified in advance.



About the project


We are upgrading the culvert under Maketū Road, at the Ōtumakoro Stream crossing, to help improve waterflow and reduce flooding during heavy rain.

The existing culvert, near Spencer Avenue West, has long been identified as a constriction point in the stormwater network, limiting how much water can pass through during significant rainfall events.

The upgrade is expected to reduce water levels upstream during storm events, decrease the frequency of flooding affecting nearby properties, and reduce how often the road closes due to overtopping at Maketū Road.


🛠️ The $550,000 project will see a second culvert installed and the existing culvert extended.


🚶 A new 2.5 metre shared pathway will also be built to improve safety for people walking and cycling through the area.


🗓️ The work is scheduled to start in early November and be completed by the end of January 2027.


🚦 Maketū Road will remain open during most of the work, but will be reduced to one lane, with temporary traffic lights in place. Short duration road closures may be required at times, but we will give you advance notice when these are coming up.


🐟 The work is being done over the summer, when water levels are lower, and to avoid the fish spawning season. Acquatic life has also been considered in the design. Raised ridges inside the culverts will create pockets of calmer water where fish can rest on their journey upstream, while fish-friendly floodgate valves will help them move through the stream.


⛏️ Archaeological monitoring will be undertaken during construction, with tangata whenua kept informed and involved throughout the project.


We know summer is a busy time in Maketū and there will be some inconvenience, but it’s the best time to do the work safely, while minimising impacts on the stream, fish and other wildlife.

We appreciate your patience while we carry out this important upgrade, which will help reduce flooding and improve the resilience of the area’s stormwater network.


Kia ora, welcome to the Maketū Road culvert upgrade project page. Here, you’ll find everything you need to know about the project, including latest updates, and a timeline of upcoming steps.

Project update - 20 November

Maketū Road night works - temporary road closures

From Sunday night, Maketū Road will be closed at the Spencer Avenue intersection for three consecutive nights while we excavate the culvert pipe.

A full road closure will give machinery and workers more room to operate safely, allowing the work to be completed faster and potentially shortening the overall project by a week or two.

Maketū Road will be closed on either side of the Spencer Avenue intersection at the following times:

• Sunday 22 November, 8pm – 4am

• Monday 23 November, 8pm – 4am

• Tuesday 24 November, 8pm – 4am

Guided access will be available for residents living in the immediate area.


Detours

Temporary traffic management and signs will be in place, with detours shown on the map below:

From the eastern side of the closure (red line):

  • Via Wilson Road, State Highway 2, Te Puke Highway (Pacific Coast Highway), and Maketū Road (red line).

From the western side of the closure:

  • Via Maketu Road, Kaituna Road, Te Tumu Road, Te Puke Highway (Pacific Coast Highway), State Highway 2 and Wilson Road and Maketū Road (blue line).
  • Alternatively, use the shorter route shown by the orange-blue lines

We appreciate that night works may cause some temporary noise disruption from machinery and lighting. Every effort will be made to minimise these impacts and complete the work as quickly and safely as possible.

Thank you for your understanding. Getting the work done in a shorter timeframe means normal traffic movements can resume sooner, reducing the overall disruption to the community.


Project Update - 11 November

We’ve appointed Joubert Pilat Limited (JPL) to carry out the culvert upgrade works, and they’re getting ready to start work on Monday 16 November, subject to the weather and necessary regulatory approvals.

Some of the materials have already arrived on site, including one of the new culvert headwalls pictured below.

These are 'split' headwalls, which means they come in one piece and are cut so they can be positioned to fit around the two culvert pipes, with the middle section concreted to complete the headwall.

Traffic management will vary as work progresses, with temporary traffic lights likely to be used for much of the project. Short road closures may also be needed for some activities, but these will be notified in advance.



About the project


We are upgrading the culvert under Maketū Road, at the Ōtumakoro Stream crossing, to help improve waterflow and reduce flooding during heavy rain.

The existing culvert, near Spencer Avenue West, has long been identified as a constriction point in the stormwater network, limiting how much water can pass through during significant rainfall events.

The upgrade is expected to reduce water levels upstream during storm events, decrease the frequency of flooding affecting nearby properties, and reduce how often the road closes due to overtopping at Maketū Road.


🛠️ The $550,000 project will see a second culvert installed and the existing culvert extended.


🚶 A new 2.5 metre shared pathway will also be built to improve safety for people walking and cycling through the area.


🗓️ The work is scheduled to start in early November and be completed by the end of January 2027.


🚦 Maketū Road will remain open during most of the work, but will be reduced to one lane, with temporary traffic lights in place. Short duration road closures may be required at times, but we will give you advance notice when these are coming up.


🐟 The work is being done over the summer, when water levels are lower, and to avoid the fish spawning season. Acquatic life has also been considered in the design. Raised ridges inside the culverts will create pockets of calmer water where fish can rest on their journey upstream, while fish-friendly floodgate valves will help them move through the stream.


⛏️ Archaeological monitoring will be undertaken during construction, with tangata whenua kept informed and involved throughout the project.


We know summer is a busy time in Maketū and there will be some inconvenience, but it’s the best time to do the work safely, while minimising impacts on the stream, fish and other wildlife.

We appreciate your patience while we carry out this important upgrade, which will help reduce flooding and improve the resilience of the area’s stormwater network.


  • Work to start on major culvert upgrade in Maketū

    Share Work to start on major culvert upgrade in Maketū on Facebook Share Work to start on major culvert upgrade in Maketū on X (formerly Twitter) Share Work to start on major culvert upgrade in Maketū on Linkedin Email Work to start on major culvert upgrade in Maketū link

    Work will soon begin on a major culvert upgrade at Maketū to help improve waterflow and reduce flooding during heavy rain.

    The $550,000 project will see a second culvert installed and the existing culvert extended under Maketū Road, at the Ōtumakoro Stream crossing. A new 2.5 metre-wide shared pathway will also be built over the crossing to improve safety for people walking and cycling through the area.

    The work is scheduled to start early November and be completed by the end of January 2027. Maketū Road will remain open during the work, but will be reduced to one lane, with temporary traffic lights in place.

    It is being done over the summer, when water levels are lower, and to avoid the fish spawning season. Acquatic life has also been considered in the design. Raised ridges inside the culverts will create pockets of calmer water where fish can rest on their journey upstream, while fish-friendly floodgate valves will help them move through the stream.

    Archaeological monitoring will be undertaken during construction, with tangata whenua kept informed and involved throughout the project.

    “It’s great to see this project getting off the ground,” says Calum Mclean, Western Bay of Plenty District Council Director Transportation.

    “We know summer is a busy time in Maketū and there will be some inconvenince, but it’s the best time to do the work safely, while minimising impacts on the stream, fish and other wildlife.

    “We appreciate people’s patience while we carry out this important upgrade, which will help reduce flooding and improve the resilience of the area’s stormwater network.”

    The existing culvert, near Spencer Avenue West, has long been identified as a constriction point in the stormwater network, limiting how much water can pass through during significant rainfall events.

    The upgrade is expected to reduce water levels upstream during storm events, decrease the frequency of flooding affecting nearby properties, and reduce how often the road closes due to overtopping at Maketū Road.

    It is being jointly funded by Western Bay of Plenty District Council ($350,000) and the Maketū Community Board ($200,000).


    Work will soon begin on a major culvert upgrade at Maketū to help improve waterflow and reduce flooding during heavy rain.

    The $550,000 project will see a second culvert installed and the existing culvert extended under Maketū Road, at the Ōtumakoro Stream crossing. A new 2.5 metre-wide shared pathway will also be built over the crossing to improve safety for people walking and cycling through the area.

    The work is scheduled to start early November and be completed by the end of January 2027. Maketū Road will remain open during the work, but will be reduced to one lane, with temporary traffic lights in place.

    It is being done over the summer, when water levels are lower, and to avoid the fish spawning season. Acquatic life has also been considered in the design. Raised ridges inside the culverts will create pockets of calmer water where fish can rest on their journey upstream, while fish-friendly floodgate valves will help them move through the stream.

    Archaeological monitoring will be undertaken during construction, with tangata whenua kept informed and involved throughout the project.

    “It’s great to see this project getting off the ground,” says Calum Mclean, Western Bay of Plenty District Council Director Transportation.

    “We know summer is a busy time in Maketū and there will be some inconvenince, but it’s the best time to do the work safely, while minimising impacts on the stream, fish and other wildlife.

    “We appreciate people’s patience while we carry out this important upgrade, which will help reduce flooding and improve the resilience of the area’s stormwater network.”

    The existing culvert, near Spencer Avenue West, has long been identified as a constriction point in the stormwater network, limiting how much water can pass through during significant rainfall events.

    The upgrade is expected to reduce water levels upstream during storm events, decrease the frequency of flooding affecting nearby properties, and reduce how often the road closes due to overtopping at Maketū Road.

    It is being jointly funded by Western Bay of Plenty District Council ($350,000) and the Maketū Community Board ($200,000).


  • $550,000 stormwater upgrade for Maketū

    Share $550,000 stormwater upgrade for Maketū on Facebook Share $550,000 stormwater upgrade for Maketū on X (formerly Twitter) Share $550,000 stormwater upgrade for Maketū on Linkedin Email $550,000 stormwater upgrade for Maketū link

    Funding has been approved for a $550,000 culvert upgrade to help reduce flooding impacts in Maketū.

    The upgrade will see a second culvert put in place under Maketū Road, and the exisiting culvert extended, to improve waterflow through the Otumakoro Stream during heavy rain.

    Inlet and outlet stuctures will also be strengthened, a 2.5m shared pathway built, and fish-friendly valves installed to protect the stream’s natural environment.

    Western Bay of Plenty District Council’s Projects and Monitoring Committee this week committed $368,000 towards the project. The remaining $182,000 is being funded by the Maketū Community Board.

    The existing culvert, near Spencer Avenue West, has long been identified as a constriction point in the stormwater network, limiting how much water can pass through during significant rainfall events.

    The upgrade is expected to reduce water levels upstream during storm events, decrease the frequency of flooding affecting nearby properties, and reduce how often the road closes due to overtopping at Maketū Road.

    "This is a project the Maketū community has been advocating for over a number of years, and we're pleased to be able to move it forward,” says Maketū-Te Puke Ward Councillor Shane Beech.

    "The upgrade won't eliminate flooding across the wider Maketū area, but it will improve the capacity of the stream crossing, and reduce pressure on the network during heavy rainfall.

    “This is a positive outcome for our community. We've seen the impact flooding can have on residents and on access through the township, so it's great to see it going ahead."

    Calum Mclean, Council’s Director Transportation, says the project balances community expectations with infrastructure priorities.

    "This project provides clear benefits for the local area and is the strongest infrastructure option available. While it isn't a complete solution to flood risk across the Maketū floodplain, it is a worthwhile investment that will improve the performance of existing infrastructure and deliver environmental benefits at the same time."

    The project includes:

    • Installation of a new 850mm concrete culvert alongside the existing 900mm culvert
    • Extension of the existing culvert
    • Construction of reinforced concrete inlet and outlet structures
    • Installation of fish-friendly flap valves to support aquatic passage while protecting against tidal intrusion
    • A new 2.5m shared concrete pathway

    Tangata whenua will be re-engaged before physical works begin, and nearby residents and other stakeholders will be notified ahead of construction.

    Project planning and procurement will now go ahead, with detailed timing for construction to be confirmed.

    Funding has been approved for a $550,000 culvert upgrade to help reduce flooding impacts in Maketū.

    The upgrade will see a second culvert put in place under Maketū Road, and the exisiting culvert extended, to improve waterflow through the Otumakoro Stream during heavy rain.

    Inlet and outlet stuctures will also be strengthened, a 2.5m shared pathway built, and fish-friendly valves installed to protect the stream’s natural environment.

    Western Bay of Plenty District Council’s Projects and Monitoring Committee this week committed $368,000 towards the project. The remaining $182,000 is being funded by the Maketū Community Board.

    The existing culvert, near Spencer Avenue West, has long been identified as a constriction point in the stormwater network, limiting how much water can pass through during significant rainfall events.

    The upgrade is expected to reduce water levels upstream during storm events, decrease the frequency of flooding affecting nearby properties, and reduce how often the road closes due to overtopping at Maketū Road.

    "This is a project the Maketū community has been advocating for over a number of years, and we're pleased to be able to move it forward,” says Maketū-Te Puke Ward Councillor Shane Beech.

    "The upgrade won't eliminate flooding across the wider Maketū area, but it will improve the capacity of the stream crossing, and reduce pressure on the network during heavy rainfall.

    “This is a positive outcome for our community. We've seen the impact flooding can have on residents and on access through the township, so it's great to see it going ahead."

    Calum Mclean, Council’s Director Transportation, says the project balances community expectations with infrastructure priorities.

    "This project provides clear benefits for the local area and is the strongest infrastructure option available. While it isn't a complete solution to flood risk across the Maketū floodplain, it is a worthwhile investment that will improve the performance of existing infrastructure and deliver environmental benefits at the same time."

    The project includes:

    • Installation of a new 850mm concrete culvert alongside the existing 900mm culvert
    • Extension of the existing culvert
    • Construction of reinforced concrete inlet and outlet structures
    • Installation of fish-friendly flap valves to support aquatic passage while protecting against tidal intrusion
    • A new 2.5m shared concrete pathway

    Tangata whenua will be re-engaged before physical works begin, and nearby residents and other stakeholders will be notified ahead of construction.

    Project planning and procurement will now go ahead, with detailed timing for construction to be confirmed.