Heartwood Avenue pedestrian bridge

Share Heartwood Avenue pedestrian bridge on Facebook Share Heartwood Avenue pedestrian bridge on Twitter Share Heartwood Avenue pedestrian bridge on Linkedin Email Heartwood Avenue pedestrian bridge link

About the project

The Heartwood Avenue pedestrian bridge is a key component of the Ōmokoroa Road urbanisation efforts, designed to connect Heartwood Avenue to Tui Glen. This project aims to enhance the connectivity and accessibility of the local community, promoting safer and more convenient pedestrian travel.

Project specifications

  • Length: 65m
  • Width: 3.5m
Construction timeline
  • Start date: November 2024
  • Completion date: June 2025


What's happening now?

31 March 2025

For the next stage of construction, our teams will be transporting very large precast concrete beams onto the site. These beams will be transported by a large truck, assisted by pilot vehicles to safely guide the load. Special temporary traffic management will be in place to ensure road user safety during this process.

There are three planned dates for these loads to be transported in:

  • Heartwood Ave - Tuesday 1 April between 6am and 12pm
  • Tui Glen - Tuesday 8 April between 6am and 12pm
  • Tui Glen - Thursday 24 April between 6am and 5pm

The route that will be affected is shown below:


To celebrate piling work being completed and to thank residents in the surrounding areas for their patience during the drilling phase, we invited them to join the project team for a coffee and walk-through of the site on Saturday 29 March. Thanks to everyone for coming!

About the project

The Heartwood Avenue pedestrian bridge is a key component of the Ōmokoroa Road urbanisation efforts, designed to connect Heartwood Avenue to Tui Glen. This project aims to enhance the connectivity and accessibility of the local community, promoting safer and more convenient pedestrian travel.

Project specifications

  • Length: 65m
  • Width: 3.5m
Construction timeline
  • Start date: November 2024
  • Completion date: June 2025


What's happening now?

31 March 2025

For the next stage of construction, our teams will be transporting very large precast concrete beams onto the site. These beams will be transported by a large truck, assisted by pilot vehicles to safely guide the load. Special temporary traffic management will be in place to ensure road user safety during this process.

There are three planned dates for these loads to be transported in:

  • Heartwood Ave - Tuesday 1 April between 6am and 12pm
  • Tui Glen - Tuesday 8 April between 6am and 12pm
  • Tui Glen - Thursday 24 April between 6am and 5pm

The route that will be affected is shown below:


To celebrate piling work being completed and to thank residents in the surrounding areas for their patience during the drilling phase, we invited them to join the project team for a coffee and walk-through of the site on Saturday 29 March. Thanks to everyone for coming!