Boucher Ave upgrades - road, water and stormwater improvements

Share Boucher Ave upgrades - road, water and stormwater improvements on Facebook Share Boucher Ave upgrades - road, water and stormwater improvements on Twitter Share Boucher Ave upgrades - road, water and stormwater improvements on Linkedin Email Boucher Ave upgrades - road, water and stormwater improvements link

This is a dedicated project page to update the community on the Boucher Avenue project.


Project Update: March 2026

Upgrades are underway along Boucher Avenue and surrounding streets to improve the stormwater system, drinking water pipes and road.

This is a coordinated project to strengthen underground infrastructure and rebuild the road surface so it is safer, more durable and better suited to everyday traffic and heavy vehicle movements.

The project has taken longer than originally planned. We appreciate the patience shown by residents, school families and growers as we work through the remaining stages.

Current status

✅ Stormwater upgrades are complete
💧 Drinking water upgrades are progressing
🚧 Road reconstruction is underway


Seasonal pause – March to September 2026

Works will pause from 31 March 2026 to 1 September 2026 to allow safer and easier movement of large orchard vehicles during the kiwifruit harvest season.

Before the pause:

  • The current road section will be completed
  • The area will be sealed and line marked
  • The pedestrian crossing will be installed
  • The site will be left safe and tidy

Works will resume in September 2026.

We will confirm the updated project timeframe once it has been finalised.


Above:

Sealing work has now been completed on Boucher Avenue, and the pedestrian crossing has reopened. The road is looking much closer to its finished state.

Above:
Before the works pause on 31 March, the team will complete final tidy-up work. This includes rolling and embedding the new chip seal, sweeping the road, carrying out small kerb repairs and finish line marking.


Why are we doing this project?

This area is a key route in Te Puke – used frequently by residents, students and families, emergency services, kiwifruit industry traffic, and others in our community. This work is essential to improve road conditions and safety, and to ensure our water and stormwater infrastructure continues to serve the community well into the future.

By coordinating all three upgrades - roading, stormwater and watermain pipes - into one project, it's more cost efficient, and we'll minimise future disruption by avoiding the need to return to the same streets later. Multiple contractors will work across the area to deliver the upgrades efficiently.


Have patai (questions), or want to kōrero with someone?


General project enquires:

Western Bay of Plenty District Council

Phone: 0800 926 732

Email: info@westernbay.govt.nz


Questions about property access:
Mike Metcalfe – Stakeholder Manager, Fulton Hogan

Phone: 027 202 9395

Email: Michael.metcalfe@fultonhogan.com


Thanks for coming along to our second Boucher Ave Community Info Session on Saturday 15 November 2025, 12:30pm - 2:30pm.


This is a dedicated project page to update the community on the Boucher Avenue project.


Project Update: March 2026

Upgrades are underway along Boucher Avenue and surrounding streets to improve the stormwater system, drinking water pipes and road.

This is a coordinated project to strengthen underground infrastructure and rebuild the road surface so it is safer, more durable and better suited to everyday traffic and heavy vehicle movements.

The project has taken longer than originally planned. We appreciate the patience shown by residents, school families and growers as we work through the remaining stages.

Current status

✅ Stormwater upgrades are complete
💧 Drinking water upgrades are progressing
🚧 Road reconstruction is underway


Seasonal pause – March to September 2026

Works will pause from 31 March 2026 to 1 September 2026 to allow safer and easier movement of large orchard vehicles during the kiwifruit harvest season.

Before the pause:

  • The current road section will be completed
  • The area will be sealed and line marked
  • The pedestrian crossing will be installed
  • The site will be left safe and tidy

Works will resume in September 2026.

We will confirm the updated project timeframe once it has been finalised.


Above:

Sealing work has now been completed on Boucher Avenue, and the pedestrian crossing has reopened. The road is looking much closer to its finished state.

Above:
Before the works pause on 31 March, the team will complete final tidy-up work. This includes rolling and embedding the new chip seal, sweeping the road, carrying out small kerb repairs and finish line marking.


Why are we doing this project?

This area is a key route in Te Puke – used frequently by residents, students and families, emergency services, kiwifruit industry traffic, and others in our community. This work is essential to improve road conditions and safety, and to ensure our water and stormwater infrastructure continues to serve the community well into the future.

By coordinating all three upgrades - roading, stormwater and watermain pipes - into one project, it's more cost efficient, and we'll minimise future disruption by avoiding the need to return to the same streets later. Multiple contractors will work across the area to deliver the upgrades efficiently.


Have patai (questions), or want to kōrero with someone?


General project enquires:

Western Bay of Plenty District Council

Phone: 0800 926 732

Email: info@westernbay.govt.nz


Questions about property access:
Mike Metcalfe – Stakeholder Manager, Fulton Hogan

Phone: 027 202 9395

Email: Michael.metcalfe@fultonhogan.com


Thanks for coming along to our second Boucher Ave Community Info Session on Saturday 15 November 2025, 12:30pm - 2:30pm.